After inspecting the stainless steel transmission chain, the power switch twisted and the starting and ending points gradually increased. With the increase of frequency and the increase of jogging distance, the stainless steel transmission chain finally reaches one cycle time. Full load operation should exceed two hours. The temperature of the roller bearing should not exceed 70 ℃ until it reaches high speed, and the load should gradually increase. The stainless steel chain plate should eventually reach overload. During the entire process of point movement, when it is found that the axis of the transmission chain conveyor is offset in the middle, the point movement should be stopped, and a part of the transmission chain should be adjusted to offset the middle structure of the running track, so that it can operate normally. Vertical, is there any intermittent condition with the support frame.
(1) The stainless steel chain plate cannot be fully loaded, terminated or started, nor can it be flipped.
(2) When feeding stainless steel chain plates, they should be evenly distributed, and the larger feeding specifications should be adjusted within the required area.
(3) Regular maintenance should be carried out on the threaded connection between the groove bottom plate and the transmission chain. If any looseness is found, it should be handled properly.
(4) Replace with new lubricating grease 7-14 days after starting the reducer, and every 3-6 months depending on the condition.